 |
|
RECENT PROJECTS
Back To Top
CONOCO
PHILLIPS - TOWER COLLAPSE |
 |
|
PROJECT DETAILS |
The 63,000 USGPM, 9 cell single flow cross flow tower located
in Burstal about 120 KM north of Medicine Hat in Alberta was
struck by a tornado in July of 2005 which resulted in the total
collapse of all 9 cells and the entire plant had to be shut down.
We visited the job site and with in days of the collapse we
were part of the team involved in supplying and setting up
over 30 portable rental cooling towers which were piped into
the existing sump, allowing the plant to be in operation within
6 weeks of the collapse.
The rental towers were in operation for approximately 2 months
while a new cooling tower was erected within the original concrete
basin.
|
Back To Top
McMASTER
UNIVERSITY - 2 CELL ADDITION |
 |
|
PROJECT DETAILS |
The customer required an additional cooling tower be added
to the following design conditions:
Flow: 3,395 usgpm
Entering Water: 95.0°F
Leaving Water: 85.0°F
Wet Bulb: 76.0°F
Site Conditions:
Install new packaged steel or build additional cells onto the
existing cross flow induced draft wood tower.
The last photograph is standing on the existing fan deck
of the original tower looking at the new two cell addition.
We had reconstructed the original tower and added the new fibreglass
fan stacks in previous years. Note: New Hot water basin joins
to original hot water basin forming one complete tower.
The third photograph shows the existing tower and in the
background with the new safety railing are the new CTM cells
that were added to the existing. |
Back To Top
ORFORD
STACK |
 |
 |
PROJECT DETAILS |
This is a one of a kind natural draft cooling tower which
was built in 1974 and is located at INCO in Sudbury.
The scope of work involved the complete removal of the entire
asbestos cement casing panels, drift eliminators, heat transfer
surface and spray system.
These asbestos components were replaced with fiberglass casing,
high efficiency PVC eliminators, high efficiency cross fluted
PVC heat transfer media and Schedule 40 PVC spray system and
nozzles.
In addition to this there was significant degradation and
spalding of the concrete sump and supporting concrete columns
and beams.
The columns were cleaned up and fitted with Stainless forms
and filled with high strength fast drying specialty grout,
all concrete beams were replaced with Steel beams and the concrete
inlet louvers were replaced using marine grade pressure treated
plywood complete with a steel guard rail.
The bulk of the work as done during the summer shutdown in
2005 & 2006, however much of the upper level columns were
done over the winter with the tower online in conditions well
below -20 Celsius. |
PROJECT TESTIMONIALS |
 |
"Your
company attained an outstanding safety record of zero injuries
over the entire construction period. We look forward to
working with you in the near future in the hope of acieving
similar safety results. "
Jim Amson, P. Eng.
Engineering Maintenance Services Group
Click
here to read a letter of reference
from our client.
|
|
Back To Top
Back To Top
Back To Top
STELCO
NANTICOKE - NEW 2 CELL MARLEY TOWER |
 |
|
PROJECT DETAILS |
The project required the simultaneous erection of a two cell
Marley Series 600 Cross Flow Cooling Tower and a single cell
Ecodyne Cross Flow Cooling Tower.
Work was completed within a very aggressive schedule, with zero
injuries or lost time. |
PROJECT TESTIMONIALS |
 |
"Thank
you to CTM for the excellent work that you did... CTM had
excellent supervision and tradesmen to do the work. Your
adherence to the AKS safety policies and routines were
faultless."
Rob Girvan, General Construction Superintendent
Aker Kvaerner Songer
Click
here to read a letter of reference
from our client.
|
|
Back To Top
STELCO
NANTICOKE - NEW ECODYNE TOWER |
 |
|
PROJECT DETAILS |
The project required the simultaneous erection of a two cell
Marley Series 600 Cross Flow Cooling Tower and a single cell
Ecodyne Cross Flow Cooling Tower.
Work was completed within a very aggressive schedule, with zero
injuries or lost time. |
PROJECT TESTIMONIALS |
 |
"Thank
you to CTM for the excellent work that you did...
CTM
had excellent supervision and tradesmen to do the work. Your
adherence to the AKS safety policies and routines were
faultless."
Rob Girvan, General Construction Superintendent
Aker Kvaerner Songer
Click
here to read a letter of reference
from our client.
|
|
Back To Top
Back To Top
TORONTO
STAR BUILDING - NEW TOWER REPLACEMENT |
 |
 |
PROJECT DETAILS |
The existing three cell Series 10 Marley Cooling Tower was
in poor condition and had to be replaced without interruption
to the operation of the plant,
This was achieved by keeping two cells in operation at all
times while each cell was completely removed and replaced.
In addition to the tower replacement, the concrete piers were
repaired and new hot dipped galvanized supporting steel was
replaced at the same time.
The new three cell Midwest Cross Flow Tower was designed to
cool 4000 USGPM from 100 to 85 @ 76 wet bulb temperature. |
Back To Top
AIR
LIQUIDE |
 |
|
PROJECT DETAILS |
Erection of two cell Midwest Induced Draft Counter flow,
each cell 30’ x 30’
|
Back To Top
B.P.
- TOWER REPAIR |
 |
|
PROJECT DETAILS |
The three cell tower was originally designed as a wet/dry
cooling tower, with mechanically operated internal dampers to
reduce the plume.
Each cell was fitted with a 12’ wide x 30’ high
finned coil on one side of the tower and the opposite side
of the tower consisted of Vee bar with 16’ air travel.
The return water from the process was pumped through the finned
coil and then through the cross over pipe and into the hot
water basin.
With plume abatement no longer an issue the system was redesigned
by Colt Engineering to cool 13,500 USGPM from 95 to 80 @ 73
wet bulb, and the project consisted of the following modifications;
- All the finned coils were completely removed
- New 20’ diameter FRP fans were installed for maximum airflow
- New hot water basins and nozzles to match water flow
- New FRP louvers
- New hangers and Vee bar
- Structural repairs
|
PROJECT TESTIMONIALS |
|
Back To Top
INCO
ACID PLANT - TOWER |
 |
|
PROJECT DETAILS |
This project involved structural repairs during the 2006
summer shutdown.
|
PROJECT TESTIMONIALS |
 |
"We
were very impressed by the professionalism that your team
displayed. The work performance was of the utmost quality."
- I.A. Chaumont, Superintendent
Chris Doyle, Plant Manager
Copper Cliff Smelter Complex
Engineering Maintenance Services Group
Click
here to read a letter of reference
from our client.
|
|
Back To Top
EATON'S
CENTER SHOPPING MALL - TOWER REPLACEMENT |
 |
|
PROJECT DETAILS |
Original Equipment: 2 cell Marley Series
15; installed 1975; Designed HH Angus
Design Conditions: 6,600 usgpm
Entering Water: 95ºF
Leaving Water: 85ºF
Wet Bulb: 76ºF
Site Conditions:
Because the system is heat recovery, the cooling tower operates all year long
therefore we were required to rebuild the system while the chilled water
plant continued to operate throughout the winter months.
The towers are located on the roof 35 stories above grade at the corner of
Yonge and Dundas Street. Crane lifts were unreasonable given the site conditions
and the height.
Photographs are of the first phase of the project. The first
shot shows the January 2004 completion of a section of the tower
while the dilapidated original section continues to operate.
The second shot is of the fibreglass casing and access door that
replaced the original MNA asbestos casing. Note the new fibreglass
fan stacks protruding from the top of the tower. |
Back To Top
Back To Top
|
 |